Footpaths finished, walls finished and painting underway- great weeks work despite the madness going on in the world





Footpaths finished, walls finished and painting underway- great weeks work despite the madness going on in the world
Tom O Brien completed the kitchen this week and Lights are fitted too. Onto painting and remaining joinery and electrical next!
Ongoing works on the stone wall including the incorporation of a stone plaque with the HAWE family name
Great work ongoing in the installation of the kitchen by Tom O’Brien
Big changes to the site as the large shed gables come down and the front wall is faced with stone
Ongoing work on the walls and masonry in the yard and at the entrance
Great work continuing by Gerry and Jimmy Condon on the stonework this week, even found an old stile into the field
Despite the bitterly cold weather and showers this week, work continues on the walls. New pier caps now in place.
Ongoing works on masonry, piers and internal doors